Mechanical auxiliaries
The equipment around the boiler: fans, ducts, dampers, tanks and hoppers, made or supplied, then installed and aligned on site.

Working principle
How it works
The working process in four steps.
Air goes in
The FD fan pushes combustion air into the furnace.
Gas is pulled out
The ID fan draws flue gas through to the stack.
Dampers set the flow
Dampers and ducts keep draught under control.
Alignment protects the train
Fan, coupling and motor are aligned to cut vibration.
Process flow chart
From order to hand-over
Diamonds are hold points: work stops until the check is signed.
- RequirementDuty and drawingHold point
- Make or sourceFabricate or buy
- InspectionDimensions and balanceHold point
- DispatchTo site
- InstallationOn foundation
- AlignmentFan to motorHold point
- Trial runVibration and temperatureHold point
- Hand-overRecords
3D model
Fan, stack and yard, in 3D
Drag to turn it. Labels name the parts we make, fit and test.
ER diagram
How every record connects
One enquiry links through to its quotation, order, jobs, inspections and dispatch, so nothing gets lost between teams.
Quality assurance plan
What gets checked
A typical plan, agreed with you for each job.
| Stage | Check | Method | Record | Role |
|---|---|---|---|---|
Drawing | Duty and connections | Drawing review | Approved drawing | H |
Fabrication | Dimensions, welds | Tape, visual | Inspection report | W |
Rotating parts | Balance | Balance record | Balance certificate | R |
Installation | Alignment | Dial gauge or laser | Alignment report | H |
Trial run | Vibration, bearing heat | Run test | Trial run report | W |
H: hold point, work stops until signed. W: witnessed. R: record reviewed.
Parts and rates
Parts and indicative rates
Indicative market rates. Your written quotation sets the final price.
| Part or service | Specification | Indicative rate |
|---|---|---|
ID and FD fans | By duty | On quotation |
Ducts and dampers | To drawing | On quotation |
Hoppers, tanks and vessels | To drawing | On quotation |
Installation and alignment | Per unit | On quotation |
Bulk orders
A 45% advance confirms your order
- Purchase orderSend your PO with the 45% advance.
- Slot confirmedProduction and the delivery date are fixed.
- Balance and dispatchThe balance follows your quotation's terms.
Rates are before GST and freight. Only your written quotation fixes the price.
Documents
What you receive
Documents on a typical job. Statutory approvals depend on the job and are agreed in the quotation.
- GA drawingDrawing
- Bill of materialsList
- Balance recordRecord
- Alignment reportReport
- Trial run reportReport