Fabrication and erection
Boiler fabrication, supply and erection
New boilers and pressure parts, made to approved drawings, delivered to your plant, erected, tested and handed over with their records.

Working principle
How it works
The working process in four steps.
Fuel burns in the furnace
Heat from the furnace passes to the water-wall tubes around it.
Water rises to the steam drum
Heated water moves up the risers. Steam separates in the drum and cooler water returns through the downcomers.
Steam leaves for the plant
Dry steam leaves the drum through the main steam line, protected by safety valves.
Flue gas gives up its heat
Hot gas passes the economiser and air heater, then the ESP, ID fan and stack.
Process flow chart
From order to hand-over
Diamonds are hold points: work stops until the check is signed.
- Drawings approvedGA and pressure part drawings signedHold point
- Material receivedHeat numbers matched to test certificatesHold point
- Cut and fit-upMarking, bending, edge preparation
- WeldingTo the approved procedure by qualified welders
- NDTRadiography or ultrasonic on pressure weldsHold point
- Dispatch to sitePacked by erection sequence
- ErectionLifting, alignment and joints
- Hydro testPressure test with inspectorHold point
- Steam blowing and first firingLines cleared, boiler lit upHold point
- Hand-overRecords and final dossier
3D model
The boiler, in 3D
Drag to turn it. Labels name the parts we make, fit and test.
ER diagram
How every record connects
One enquiry links through to its quotation, order, jobs, inspections and dispatch, so nothing gets lost between teams.
Quality assurance plan
What gets checked
A typical plan, agreed with you for each job.
| Stage | Check | Method | Record | Role |
|---|---|---|---|---|
Incoming material | Grade, size, heat number | Test certificate and PMI | Material register | H |
Fit-up | Root gap, alignment | Weld gauge | Fit-up report | W |
Welding | Procedure and welder qualified | WPS, PQR, WPQ review | Weld log | R |
Pressure welds | Internal soundness | RT or UT | NDT report | H |
Erection | Level, plumb, drum position | Survey and alignment | Erection report | W |
Final | Tightness at test pressure | Hydrostatic test | Hydro test certificate | H |
H: hold point, work stops until signed. W: witnessed. R: record reviewed.
Parts and rates
Parts and indicative rates
Indicative market rates. Your written quotation sets the final price.
| Part or service | Specification | Indicative rate |
|---|---|---|
Steam drum | Rolled shell, dished ends, nozzles | On quotation |
Headers and tube panels | Water walls and bank tubes | On quotation |
Boiler tube, seamless | SA 210 Gr A1 | ₹85 to ₹170 per kg |
Boiler safety valve | Spring or dead weight, by size | ₹9,000 to ₹14,000 per piece |
Water level gauge | Tubular to reflex, by pressure | ₹2,000 to ₹14,000 per piece |
Erection of complete boiler | Crew, tools and supervision | On quotation |
Bulk orders
A 45% advance confirms your order
- Purchase orderSend your PO with the 45% advance.
- Slot confirmedProduction and the delivery date are fixed.
- Balance and dispatchThe balance follows your quotation's terms.
Rates are before GST and freight. Only your written quotation fixes the price.
Documents
What you receive
Documents on a typical job. Statutory approvals depend on the job and are agreed in the quotation.
- General arrangement drawingDrawing
- Bill of materialsList
- Material test certificatesCertificate
- WPS, PQR and welder recordsProcedure
- NDT reportsReport
- Hydro test certificateCertificate
- Erection and alignment reportReport
- Final hand-over dossierDossier
Enquiry
Ask about boilers
Share the work, the plant and your timeline. You will receive a written quotation.